What is Network Sensitivity?
In project management, a network diagram is said to be "sensitive" when there is little flexibility in the scheduling of activities, and any delay in a critical path activity will…
In project management, a network diagram is said to be "sensitive" when there is little flexibility in the scheduling of activities, and any delay in a critical path activity will…
A network diagram in the context of project management is called so because it visually represents the relationships and dependencies between different activities or tasks within a project. The term…
Network sensitivity is a vital concept in IT project management that helps project managers understand which activities have the most significant impact on a project's schedule. By identifying critical and near-critical activities, project managers can proactively manage risks, allocate resources effectively, and communicate potential schedule impacts to stakeholders.
Both free slack and total slack are valuable tools for project managers to assess schedule flexibility, manage resources, and make informed decisions to ensure that the project stays on track and meets its deadlines.